"South Palmer Lane will be closed for short periods to allow for the reconstruction and widening. No closures are anticipated for SH-44 or the north leg of Palmer Lane." That line from the Idaho Transportation Department's SH-44 and Palmer Lane Traffic Signal page is the most local sentence in all the paperwork behind the coming roadwork near Star. Riverstone sits at the southwest corner of N. Palmer Lane and W. Moon Valley Road, south of the highway. Every closure ITD expects at this intersection falls on Riverstone's side of SH-44.
Two separate projects meet at that corner over the next year. They have different contracts, different start dates and different finish lines. The bigger one gets most of the attention. For anyone who drives Palmer Lane every day, the smaller one matters more.
Two Contracts, One Intersection
The first is ITD's widening of State Highway 44 to five lanes between Star Road and SH-16. That means two travel lanes each way plus a center turn lane, a new road surface, utility relocation and connected pedestrian pathways along the south side. In ITD's highway program, the Palmer Lane intersection sits at milepost 13.023, inside the widening's span of mileposts 10.523 to 16.150.
The second is a traffic signal at SH-44 and Palmer Lane. ITD is designing it with the Ada County Highway District and the cities of Star and Eagle, and it has its own project page, scope and schedule.
| SH-44 widening | Palmer Lane signal | |
|---|---|---|
| What it builds | Five lanes, Star Road to SH-16 | Signal, turn lanes, crosswalks at Palmer |
| Who runs it | ITD, built by Knife River | ITD with ACHD, Star and Eagle |
| Start | November 2026, per Star | Utility and irrigation work in 2026; roadway work spring 2027 |
| Length | Into fall/winter 2027, per ITD | About six months of construction |
| Closures expected | No full SH-44 closures | Short closures of south Palmer Lane only |
The table shows why the two are easy to confuse. Both are ITD projects at the same corner in the same year, but they run on separate timelines.
The Widening Arrives First, and Arrived Early
The widening was not supposed to start this soon. The City of Star's September 1, 2026 transportation report lists it as moved up from 2029. The report says the bid "came in half of what was anticipated," with an awarded cost of $5,384,589, and puts the start in November 2026 and the end in October 2027. ITD's project page gives the finish as fall/winter 2027 and says utility and paving work begins this fall as weather permits.
For the next several months, most of the work will happen beside the road. ITD's drop-in display boards, shared at Liberty Hall in Star on October 22, lay out the order. Utilities get relocated first. Asphalt is removed and replaced in the first two phases. Temporary pavement and a traffic shift come in the third. Widening and road-base work follow in the fourth and fifth phases, with new asphalt last.
ITD's rules for drivers are consistent across its materials:
- At least one lane stays open in each direction on SH-44 during the day.
- No full closures of SH-44 are anticipated.
- Drivers should expect four traffic shifts, each moving traffic to the side opposite the work.
- Overnight lane closures and flagging may be needed, including at intersections and between phases.
- Nighttime work will bring equipment noise and backup alarms.
- Local roads stay open, but some turns will be restricted, so a usual route may change.
The last item matters most for a Palmer Lane driver. ITD has not said which side of the highway gets worked first. During some shifts, a left turn out of Palmer may not be available, and the detour depends on which phase is active.
Spring 2027 Is When Both Projects Work Riverstone's Side
The signal project has its own history. ITD finished its SH-44 project from Star Road to West State Street in 2024, and that work identified the need for a higher-capacity intersection at Palmer Lane. ITD calls the signal an interim improvement that adds protected movements to keep up with recent growth.
Its schedule, per ITD's FAQ:
- Environmental evaluation and construction plans, which ITD expected to finish in early 2026.
- Advertising for a construction contract, expected later in 2026.
- Right-of-way acquisition once plans are approved.
- Utility and irrigation work, expected to begin in 2026.
- Roadway construction starting in spring 2027 and lasting about six months.
ACHD's five-year work plan, dated September 25, 2026, also lists the joint interim signal for 2027 construction. The widening's own timeline shows "widening & paving operations continue" in spring 2027. So the signal's roadway season overlaps the busiest stretch of the widening. Knife River runs the widening, and ITD has not named a contractor for the signal.
The physical work explains why the closures fall on the south side. ITD plans to widen the south leg of Palmer Lane to add a dedicated left-turn lane. It will also build new ADA curb ramps at the southwest and southeast corners and add marked crosswalks across the south and east sides of the intersection. All of that reconstruction sits on the leg that runs toward Moon Valley Road, which is why ITD expects short closures of south Palmer and none on the north leg.
The Finish Line Belongs to a Third Project
Even after the widening's crews are done, the new lanes will not open on their own schedule. ITD's FAQ says the widening's opening "will coincide with the State Highway 16 and State Highway 44 Interchange opening." That interchange is part of the SH-16 extension south to I-84.
ITD's October 15, 2026 SH-16 newsletter puts the I-84 to SH-44 corridor at 60% complete and expects it to open in mid-2027. Star's September report lists the SH-44/16 interchange, a $79.5 million piece, for completion in summer 2027. Until then, ITD stresses that the new SH-16 corridor is an active work zone, and motorists and pedestrians may not use it.
These dates do not line up exactly. The interchange and the corridor are targeted for summer or mid-2027. ITD lists the widening's construction as complete in fall/winter 2027, and Star lists October 2027, yet ITD also says the widening opens alongside the interchange. Taken together, ITD's materials tie the five new lanes past Palmer Lane to the interchange schedule as well as the widening's own. Any change to either one changes when Riverstone drivers get the finished road.
Some related work has stalled. Star's report marks two ITD projects as delayed by state funding cuts. One is the widening of SH-16 from SH-44 to Beacon Light Road, which includes the Floating Feather overpass. The other is the US 20/26 widening west of Star Road. The SH-44 segment past Palmer Lane is moving faster than the projects around it.
What the Corner Looks Like When It Is Done
Today, Palmer Lane meets SH-44 at a two-way left-turn lane with no signal. ITD's signal scope replaces that center lane with dedicated left-turn lanes at the intersection. It also adds new pavement at the northwest corner so eastbound drivers can make a U-turn to head west.
The pathway pieces add up over time. The widening connects pedestrian pathways on the south side of SH-44. ITD says that work links into a separate, future multi-use pathway, 10 to 12 feet wide, from SH-16 to West State Street, and the signal project prepares the Palmer corner for it. Star's report lists a related pathway along the south side of SH-44 from Star Road to Ballentyne Lane for fiscal year 2029. ACHD's September 2026 plan also includes undated future items near Palmer Lane, Moon Valley Road and SH-44. The Palmer Lane entry calls for sidewalks on both sides of the street, bike facilities, upgraded ramps and streetlights. They are on the list, but not on a construction calendar.
ITD sends updates as the work moves through its phases. Text 44WIDENING to 1-866-483-8422, or email [email protected], for widening notices. The signal project page is the place to watch for the south Palmer closure dates as they are set.